Overview

Not long after finishing off the room over our attached garage, we realized that storage was going to be a problem. We have an attic, but it is only accessible with a pull down ladder. This makes it difficult to get large or heavy items up there like furniture, etc. Additionally, our garage is quite small, and with the landing to get into the house, there isn’t enough room for the cars *and* my stuff.

This spring, we decided we wanted to build a detached garage with a storage room that I can use as a workshop and get all of the junk out of the attached garage so that we can actually use it for the cars. Initially we thought we wanted a 16′ x 24′. Here is a rendition of what it would look like.
garage1.jpg

After spending some time sketching it up, we concluded that we wanted something a little bigger and settled on a 20′ x 30′ garage based on where we wanted to put it and the trees we wanted to keep.

We started to look for a general contractor to do the work since there were some other projects that we wanted to work on. We ended up getting 4 different bids that ranged from $36,000 to $43,000. Eeks! That was way outside what I thought it should cost. Feeling very frustrated, I started to spec out what it would take to build it myself. I worked as a framer one summer while I was in school and didn’t feel that this was outside my ability. The plan was to hire someone to do the foundation work and I would do the rest.

During this, I collected the names of a bunch of subcontractors for various pieces (footing, masonry, framing, roofing, etc.) and decided to make some calls. After talking with Paul (a framer), I felt that just acting as the general contractor would keep me busy enough.

As things stand now, I’m acting as the general contractor. Below are the various phases of the project. I will update as this project progresses.

Building Permit

At this point, I needed to spin up on the current codes for our county. Their website had a lot of good information and anything that was missing, they were more than willing to talk to me about it and answer any questions. I submitted my plans on August 10th. I had to make one small correction and received approval on August 17th.
garageplans1.jpg garageplans2.jpg garageplans3.jpg garageplans4.jpg garageplans6.jpg garageplans5.jpg garageplans7.jpg garageplans8.jpg garageplans9.jpg garageplans10.jpg garageplans11.jpg

Tree and Stump Removal

There were a number of trees in the backyard where we wanted to build the garage. Also, we had a small shed that we need to move out of the way. I hired Chris to take down all the trees and haul it all away. If it was just a couple of small to medium trees, I would have done it myself, but one was a huge forked tree that hung over the shed and I didn’t feel comfortable tackling that one myself.

After the trees were down, I rented a backhoe to remove the stumps. My brother-in-law Howie, hooked me up with a good rate on a full size backhoe, and my friend Les (he used to work as an excavator) and my Dad came over and helped dig the stumps out and move the shed.

While I was at it, I used the backhoe to move the bushes that were around the shed. A bit overkill but fun.

I then set up batter boards for marking the exact placement of the stakes for the footing.
wbsiv_070713_6214.jpg wbsiv_070713_6215.jpg wbsiv_070713_6221.jpg wbsiv_070714_04013.jpg wbsiv_070715_04036.jpg wbsiv_070805_6372.jpg wbsiv_070805_6376.jpg

Footing

Dan came out and dug and poured the footing on August 7. Normally an engineer is used to inspect the footing prior to pouring the concrete. However, Dan said he would wait for the county inspector to come out so I could save the engineering fees. The inspector was very cooperative and came out shortly after Dan was done digging. The only problem we ran into was Dan estimated 8 1/2 yards of concrete and came up half a yard short so we had to wait another hour for a second truck.

wbsiv_070807_04209.jpg wbsiv_070807_6377.jpg wbsiv_070807_6380.jpg wbsiv_070807_6383.jpg wbsiv_070807_6384.jpg wbsiv_070807_6385.jpg wbsiv_070807_6387.jpg wbsiv_070807_6390.jpg wbsiv_070807_6391.jpg wbsiv_070807_6392.jpg wbsiv_070807_6396.jpg

Foundation Walls

The foundation walls were pretty straight forward and were completed in one day.

wbsiv_070811_6399.jpg wbsiv_070811_6401.jpg wbsiv_070811_6403.jpg wbsiv_070811_6407.jpg

Backfill

Once the foundation walls were complete, we had to go back and fill in before pouring the slab. We rented a compactor and Les brought his tractor over one afternoon to spread the first 20 tons of #57s (crushed rock). We’d spread a couple of inches, then run the compactor. We quickly realized that it wasn’t enough and I ordered another 17 tons. Unfortunately Les was busy on the weekend and we had to move the remaining 17 tons by hand. We recruited a bunch of family for this effort. Fortunately Ben was able to bring his 4 wheeler which has an attached blade on it. That worked extremely well for grading the dirt around the outside of the foundation but struggled with moving the rock. Still, it saved a bunch of time and effort since it was still quicker than with just shovels.

wbsiv_070815_04233.jpg wbsiv_070815_04236.jpg wbsiv_070815_04240.jpg wbsiv_070815_04247.jpg wbsiv_070815_04252.jpg wbsiv_070816_04257.jpg wbsiv_070816_04259.jpg wbsiv_070818_04267.jpg wbsiv_070818_04269.jpg wbsiv_070818_04274.jpg wbsiv_070818_04280.jpg wbsiv_070818_04281.jpg wbsiv_070818_04282.jpg wbsiv_070818_04295.jpg

Slab

With the fill done, Jimmy’s concrete crew was able to come in and pour and smooth the slab in about half a day. Boy does it look good. They are coming back this week to seal it.

wbsiv_070824_6408.jpg wbsiv_070824_6409.jpg wbsiv_070824_6411.jpg wbsiv_070824_04301.jpg wbsiv_070824_04305.jpg wbsiv_070824_04325.jpg wbsiv_070824_6412.jpg

Framing

In order to avoid lumber price increases in September, they delivered the framing materials on Aug 31. Paul and his team started framing the following Friday. The framing was finished on October 1st and it passed the veneer inspection the next day. One note, Randy (the lumber yard rep) gave me the house wrap and the flashing that was left over from a sponsored project. This saved me about $200.

wbsiv_070907_04366.jpg wbsiv_070907_04356.jpg wbsiv_070907_04368.jpg wbsiv_070907_04373.jpg wbsiv_070907_04375.jpg wbsiv_070907_04376.jpg wbsiv_070907_04377.jpg wbsiv_070907_04383.jpg wbsiv_070907_04384.jpg wbsiv_070907_04386.jpg wbsiv_070907_04387.jpg wbsiv_070911_04407.jpg wbsiv_070911_04410.jpg wbsiv_070911_04411.jpg wbsiv_070911_04416.jpg wbsiv_070911_04418.jpg wbsiv_070913_6415.jpg wbsiv_070913_6416.jpg wbsiv_070913_6417.jpg wbsiv_070913_6419.jpg wbsiv_070913_6420.jpg wbsiv_070913_6421.jpg wbsiv_071006_6566.jpg wbsiv_071006_6568.jpg wbsiv_071006_6569.jpg

Roof

While we were waiting on the stairs, etc., the roofers came out and put down the shingles, so the roof is now done. We had to switch to a ridge vent from the originally planned gable vents because there really wasn’t much room for the gable vents.

wbsiv_070917_04442.jpg wbsiv_070917_04443.jpg wbsiv_070917_04444.jpg wbsiv_070917_04446.jpg wbsiv_070917_04447.jpg

Overhead Doors

On October 3rd, the overhead doors were installed. They consisted of a 16′ x 8′ door, a specially cut 6′ x 7′ door and the opener for the larger door.

wbsiv_071006_6563.jpg wbsiv_071006_6564.jpg wbsiv_071006_6567.jpg

Siding

Earl and his team came in and finished the siding in a day and a half. It looks great!

wbsiv_071011_04536.jpg wbsiv_071011_04538.jpg wbsiv_071011_04540.jpg wbsiv_071011_6630.jpg wbsiv_071011_6632.jpg wbsiv_071011_6631.jpg

Electrical

I’ve been talking with Doug (a master electrician), the county, my dad (he’s an EE that does industrial work) and the electrical supply shop. I basically have a plan in place. The service will be a 100A/240V sub panel off the main panel. While I have the trench dug for the subpanel lines, I’m also going to run a line for the generator so that the generator can be back by the garage. This will tie into the main panel with a main breaker interlock.

The electrical rough is complete. All the lines have been pulled, the sub-panel wired, and most of the outlets installed.

wbsiv_071124_04656.jpg wbsiv_071124_04665.jpg wbsiv_071125_04666.jpg wbsiv_071202_04673.jpg wbsiv_080108_7137.jpg wbsiv_080108_7139.jpg wbsiv_080108_7142.jpg wbsiv_080108_7143.jpg wbsiv_080108_7145.jpg wbsiv_080108_7150.jpg

Finish work

In addition to all the necessary inspections, etc. the finishing work consists of insulating, installing pegboard on the first floor, hand rail for the stairs (required by code), painting the side door and trim to match the house, and a couple of trucks of fill dirt for the back yard. So far, one truck load of dirt has been brought in and the driveway has been repaved to blend in the garage.

wbsiv_071210_04675.jpg wbsiv_071210_04682.jpg wbsiv_071210_04686.jpg wbsiv_080108_7151.jpg

Budget vs Actual Cost

Below is a table showing what we budgeted versus the actual cost for each phase. In some cases there were things that I had missed or underestimated, in others we made changes that increased the final cost.

Description Estimate Actual
Tree Removal1 $900 $1,400.00
County Permit2 $250 $440.72
Backhoe Rental3 $385 -
Footing (labor & materials) $1,650 $1,563.85
Foundation (labor & materials)4 $4,040 $6,500.00
Slab (labor & materials)5 $1,500 $2,452.30
Framing (labor & materials)6 $9,915 $8,438.66
Roof (labor & materials)7 $1,213 $1353.00
Overhead Doors $1,934 $1,934.00
Siding (labor & materials) $3,460 $3,210.19
Electrical (labor & materials) $350 -
Misc (pegboard, insulation, etc) $1,000 -
TOTAL $26,597 $28,075.42
  1. added a couple of extra trees
  2. estimate didn’t include electrical permit or levys
  3. unplanned expense
  4. extra block, brick required, didn’t include mortar, etc.
  5. estimate didn’t include fill material or compactor rental
  6. used pvc to frame the overhead doors which was more expensive
  7. added ridge vent

Hall of Fame

Although I took on contracting this project myself, I have received a huge amount of help.

  • Martinah
  • Billy
  • Martin
  • Les
  • Dad
  • Mom
  • Howie
  • Howard
  • Ben
  • Brian
  • Bradley
  • Adam
  • Jon
  • Steve
  • Gary and crew
  • Dan
  • Phillip and crew
  • Jimmy and crew
  • Eddie
  • Paul and crew
  • Randy
  • Todd
  • Crystal
  • Doug and Earl
  • Earl (different one)